Free tool
Do I need a CDM principal designer?
Six questions, a plain answer, and the reasoning shown. Nothing to buy and no email address needed.
This tool gives general guidance from the answers you type. It is not legal advice about your project, and it cannot see your drawings or your site. Where a project is unusual the answer is a conversation rather than a checker. How we write this.
What this checker is doing
It walks the same sequence the regulations do, in the order they apply.
- Is it construction work carried out on your behalf?
If you are doing it yourself on your own home, HSE's decision chart treats it as DIY and CDM 2015 does not apply.
- Domestic client or not?
This decides whether regulation 7 reallocates the client duties, and what happens if nobody is appointed.
- More than one contractor?
The single trigger in regulation 5(1). Subcontractors count and do not have to overlap.
- Has an appointment been made in writing?
If yes, regulation 5 is satisfied. If no, regulation 5(3) or regulation 7(2) decides where the duties have already gone.
- Who controls the design?
On a domestic project with no appointment, regulation 7(2) puts the role on the designer in control of the pre-construction phase.
- Has work started?
Does not change whether the appointment is required. It changes how much of the role is still recoverable.
Sources
- CDM 2015, regulation 5 legislation.gov.uk
- CDM 2015, regulation 7 legislation.gov.uk
- CDM 2015, regulation 15 legislation.gov.uk
- Managing health and safety in construction, L153, Appendix 6 HSE guidance